Enable checkout
Security admins can define which accounts have checkout enabled and set the maximum checkout time. They can also override the max checkout time when creating a policy and force a checkin on one or many accounts during a threat detection.
Before you begin
- 
                                                            
A resource group is already created.
 - 
                                                            
You must have the Okta Privileged Access security admin role.
 - 
                                                            
The account is added to Privileged Accounts in the Project Settings.
 - 
                                                            
Review Requirements and limitations.
 
Start the task
Limit access to shared accounts for a single user and control the maximum amount of time that they're allowed to access the resources.
- 
                                                            
Open the Okta Privileged Access dashboard.
 - 
                                                            
Click Resource Management.
 - 
                                                            
Select the resource group that contains the project you want to configure.
 - 
                                                            
Select an available project.
 - 
                                                            
Click the dropdown menu, and then select a Resource type.
 - 
                                                            
Go to the Settings tab.
 - 
                                                            
Click Edit on Checkout Settings.
 - 
                                                            
Select Enable Checkout for, and then complete the following steps:
- 
                                                                    
Select one of the following options:
- 
                                                                            
Include managed resources
 - 
                                                                            
Exclude resources
 - 
                                                                            
Include resources
 
 - 
                                                                            
 - 
                                                                    
If you click Exclude resources, select the resources you want to exclude.
 - 
                                                                    
If you click Include resources, select the resources you want to include.
 - 
                                                                    
Select the maximum checkout time. By default the checkout time is set to 30 minutes.
 
 - 
                                                                    
 - 
                                                            
Click Save.
 